Productivity of work of tiling the floor should be a concern for the contractor because
the result depends on the skills and abilities ceramist. The purpose of this research is to
determine the level of productivity ceramist taking into account of the work achieved
and to determine the factors that affect productivity in the work ceramist ceramic
couple floors of the building. The method used in this research is descriptive method.
Productivity values obtained are : ceramist 1 of 0,0420 m2
/min; conductor 1 of 0,0394
m
2
/min; ceramist 2 of 0,0368 m2
/min; conductor 2 of 0,0347 m2
/min; ceramist 3 of
0,0290 m2
/min; conductor 3 of 0,0277 m2
/min; ceramist 4 of 0,0280 m2
/min; conductor
4 of 0,0265 m2
/min; ceramist 5 of 0,0283 m2
/min; conductor 5 of 0,0265 m2
/min.
Keywords : Ceramist, productivity